Project cost · modeled example · 8 builds

Cost to Cut a Basement Floor for Plumbing: $1,763 to $8,371

Cutting a basement floor for a bathroom drain costs about $1,763 to $2,712 for cutting and patching a 12 ft basement slab trench up to $5,441 to $8,371 for the drains for a three-piece basement bathroom. Eight basement jobs priced line by line, from a 12 ft slab trench to a full bathroom's drains: the tie-in to old cast iron, an ejector pit, an up-flush toilet, a raised platform, a laundry sink and the camera inspection first. Every line itemized, with crew hours.

Direct answer: Cutting a basement floor for a bathroom drain costs about $1,763 to $2,712 for cutting and patching a 12 ft basement slab trench up to $5,441 to $8,371 for the drains for a three-piece basement bathroom, from a direct job cost of $1,356 and $4,186. Direct job cost is labor and materials only, with no contractor overhead or profit, and is not a price: no contractor performs work at job cost. Permit and inspection fees are not included.

Eight builds, side by side

Eight jobs on the same researched rates: the concrete work alone, a bathroom's drains, the tie-in at the stack, three fixes for a sewer that is too shallow (an ejector pit, an up-flush toilet, a raised platform), a laundry sink and the camera inspection to do first.

BuildJob costLaborCrew hoursMaterialsIllustrative selling price
A. 12 ft trench, concrete only$1,356$7809 to 16 h$126$1,763 to
$2,712
B. Bathroom drains, 20 ft$4,186$3,29030 to 43 h$446$5,441 to
$8,371
C. Tie-in at the cast iron stack$2,344$1,82310 to 15 h$296$3,047 to
$4,688
D. Sewage ejector pit$4,231$2,46520 to 29 h$1,316$5,500 to
$8,462
E. Up-flush toilet$3,132$1,61512 to 18 h$1,517$4,071 to
$6,264
F. Raised platform over the drains$1,222$85510 to 18 h$367$1,589 to
$2,444
G. Laundry sink, 10 ft trench$3,659$2,85024 to 32 h$359$4,756 to
$7,318
H. Camera and locate first$325$3251 to 2 h$0$423 to
$650

Materials include allowances. Illustrative selling price is the job cost at a 30% to 100% markup; your price depends on your own overhead and profit. Labor hours are a planning range and include setup, daily cleanup and material runs; they are never a charge to the customer. Permit and inspection fees are not included; requirements vary by jurisdiction.

Which price is closer to yours?

  • Lean, +30%: A handyman or owner-operator who does the work with a small crew and no office. Usually the lowest quote. The owner handles scheduling, questions and callbacks around the work itself.
  • Standard, +50%: A remodeling company with a crew, an office, insurance and someone to answer the phone. Close to the average remodeler's overhead in the National Association of Home Builders cost-of-doing-business survey.
  • Full-Service, +100%: A design-build firm with designers, a salesperson and a project manager who runs the job. The extra pays for planning, coordination and one point of contact from design to final inspection.

Higher markup means more business behind the job, not by itself better work, and a lower markup is not by itself a better deal. For contractors: how each markup splits into overhead and profit is in the overhead categories guide.

Each build in detail

A. 12 ft trench, concrete only: $1,356

Saw-cut, break out, dig 18 in deep, haul, gravel backfill and a concrete patch; the plumbing is by others. Labor is $780 of the $1,356 job cost, or 57.5%. It is about 9 to 16 hours of work, including setup, daily cleanup and material runs.

Labor cost by trade

Labor only. Materials, allowances and dump fees are in the line items below. Hours are person-hours at typical production from Clamp’s labor hours catalog, as a range: a planning figure, not a schedule and not a charge to the customer.

TradeHoursLabor costLean×1.30Standard×1.50Full-Service×2.00
Plumbing7 to 14 h$780$1,014$1,170$1,560
Setup, cleanup and material runs1 to 3 hin the prices
All labor9 to 16 h$780$1,014$1,170$1,560

Every line item

Labor $780 + materials and allowances $126 + dump fees and other $450 = $1,356 direct job cost. Hours are person-hours at typical production, on labor rows only, and the direct-cost row adds about 15% for setup, daily cleanup and material runs; an allowance or material row names the labor line that installs it, and a subcontract row has none, because the sub’s price includes their own time. Some labor quantities include a difficulty factor, so they can exceed the measured area; each row’s derivation is in the downloadable data.

ItemQtyUnitHoursLaborMaterialLine cost
Demo & Prep
Debris Haul-Off (per Load)1ea$0$0$225
Demo & Prep subtotal$225
Demo & Prep subtotal$225
Plumbing
Slab Cutting Equipment and Dust Control (per job)1ea$0$0$225
Slab Saw-Cut and Trench (per lf)12lf5 to 12 h$576$0$576
Slab Trench Patch Labor12lf1 to 4 h$204$0$204
Slab Trench Patch Materials (per lf)Labor on: Slab Trench Patch Labor12lf$0$126$126
Plumbing subtotal7 to 14 h$1,131
Plumbing subtotal7 to 14 h$1,131
DIRECT JOB COST9 to 16 h$1,356
DIRECT JOB COST9 to 16 h$1,356

B. Bathroom drains, 20 ft: $4,186

Toilet, shower and sink drains in 20 ft of trench, tied into the old drain, tested, inspected and patched. Labor is $3,290 of the $4,186 job cost, or 78.6%. It is about 30 to 43 hours of work, including setup, daily cleanup and material runs.

Labor cost by trade

Labor only. Materials, allowances and dump fees are in the line items below. Hours are person-hours at typical production from Clamp’s labor hours catalog, as a range: a planning figure, not a schedule and not a charge to the customer.

TradeHoursLabor costLean×1.30Standard×1.50Full-Service×2.00
Plumbing25 to 38 h$3,290$4,277$4,935$6,580
Setup, cleanup and material runs2 to 8 hin the prices
All labor30 to 43 h$3,290$4,277$4,935$6,580

Every line item

Labor $3,290 + materials and allowances $446 + dump fees and other $450 = $4,186 direct job cost. Hours are person-hours at typical production, on labor rows only, and the direct-cost row adds about 15% for setup, daily cleanup and material runs; an allowance or material row names the labor line that installs it, and a subcontract row has none, because the sub’s price includes their own time. Some labor quantities include a difficulty factor, so they can exceed the measured area; each row’s derivation is in the downloadable data.

ItemQtyUnitHoursLaborMaterialLine cost
Demo & Prep
Debris Haul-Off (per Load)1ea$0$0$225
Demo & Prep subtotal$225
Demo & Prep subtotal$225
Plumbing
Below-Slab Drain Pipe Install (per lf)20lf3 to 9 h$680$0$680
Drain Water Test and Rough-In Inspection (per job)1ea1 to 2 h$325$0$325
Tie-In Wye and Transition Couplings (per tie-in)1ea$0$98$98
DWV MaterialsLabor on: Below-Slab Drain Pipe Install (per lf)22lf$0$138$138
Slab Cutting Equipment and Dust Control (per job)1ea$0$0$225
Slab Saw-Cut and Trench (per lf)20lf9 to 19 h$960$0$960
Slab Trench Patch Labor20lf2 to 6 h$340$0$340
Slab Trench Patch Materials (per lf)Labor on: Slab Trench Patch Labor20lf$0$210$210
Tie In to the Existing Cast Iron or Clay Drain (per tie-in)1ea1 to 4 h$560$0$560
Vent Extension Labor1ea2 to 6 h$425$0$425
Plumbing subtotal25 to 38 h$3,961
Plumbing subtotal25 to 38 h$3,961
DIRECT JOB COST30 to 43 h$4,186
DIRECT JOB COST30 to 43 h$4,186

C. Tie-in at the cast iron stack: $2,344

A 3 by 3 ft opening at the stack, a wye with matched couplings, a cleanout, a test and the patch. Labor is $1,823 of the $2,344 job cost, or 77.8%. It is about 10 to 15 hours of work, including setup, daily cleanup and material runs.

Labor cost by trade

Labor only. Materials, allowances and dump fees are in the line items below. Hours are person-hours at typical production from Clamp’s labor hours catalog, as a range: a planning figure, not a schedule and not a charge to the customer.

TradeHoursLabor costLean×1.30Standard×1.50Full-Service×2.00
Masonry3 to 7 h$650$845$975$1,300
Plumbing4 to 8 h$1,173$1,525$1,760$2,346
Setup, cleanup and material runs1 to 3 hin the prices
All labor10 to 15 h$1,823$2,370$2,735$3,646

Every line item

Labor $1,823 + materials and allowances $296 + dump fees and other $225 = $2,344 direct job cost. Hours are person-hours at typical production, on labor rows only, and the direct-cost row adds about 15% for setup, daily cleanup and material runs; an allowance or material row names the labor line that installs it, and a subcontract row has none, because the sub’s price includes their own time. Some labor quantities include a difficulty factor, so they can exceed the measured area; each row’s derivation is in the downloadable data.

ItemQtyUnitHoursLaborMaterialLine cost
Masonry
Sewer Cleanout Slab Break Labor1ea3 to 7 h$650$0$650
Masonry subtotal3 to 7 h$650
Masonry subtotal3 to 7 h$650
Plumbing
Drain Water Test and Rough-In Inspection (per job)1ea1 to 2 h$325$0$325
Tie-In Wye and Transition Couplings (per tie-in)1ea$0$98$98
Sewer Cleanout AssemblyLabor on: Sewer Cleanout Install Labor1ea$0$156$156
Sewer Cleanout Install Labor1ea1 to 3 h$288$0$288
Slab Cutting Equipment and Dust Control (per job)1ea$0$0$225
Slab Trench Patch Materials (per lf)4lf$0$42$42
Tie In to the Existing Cast Iron or Clay Drain (per tie-in)1ea1 to 4 h$560$0$560
Plumbing subtotal4 to 8 h$1,694
Plumbing subtotal4 to 8 h$1,694
DIRECT JOB COST10 to 15 h$2,344
DIRECT JOB COST10 to 15 h$2,344

D. Sewage ejector pit: $4,231

A sealed basin and pump in the slab with vent, check valve, shutoff and 15 ft of discharge. Labor is $2,465 of the $4,231 job cost, or 58.3%. It is about 20 to 29 hours of work, including setup, daily cleanup and material runs.

Labor cost by trade

Labor only. Materials, allowances and dump fees are in the line items below. Hours are person-hours at typical production from Clamp’s labor hours catalog, as a range: a planning figure, not a schedule and not a charge to the customer.

TradeHoursLabor costLean×1.30Standard×1.50Full-Service×2.00
Plumbing17 to 25 h$2,465$3,205$3,698$4,930
Setup, cleanup and material runs1 to 5 hin the prices
All labor20 to 29 h$2,465$3,205$3,698$4,930

Every line item

Labor $2,465 + materials and allowances $1,316 + dump fees and other $450 = $4,231 direct job cost. Hours are person-hours at typical production, on labor rows only, and the direct-cost row adds about 15% for setup, daily cleanup and material runs; an allowance or material row names the labor line that installs it, and a subcontract row has none, because the sub’s price includes their own time. Some labor quantities include a difficulty factor, so they can exceed the measured area; each row’s derivation is in the downloadable data.

ItemQtyUnitHoursLaborMaterialLine cost
Demo & Prep
Debris Haul-Off (per Load)1ea$0$0$225
Demo & Prep subtotal$225
Demo & Prep subtotal$225
Plumbing
Drain Water Test and Rough-In Inspection (per job)1ea1 to 2 h$325$0$325
DWV Install Labor5lf1 to 4 h$225$0$225
DWV MaterialsLabor on: DWV Install Labor16.5lf$0$103$103
Sewage Ejector Basin and PumpLabor on: Sewage Ejector Install1ea$0$1,150$1,150
Sewage Ejector Install1ea5 to 11 h$1,100$0$1,100
Slab Cutting Equipment and Dust Control (per job)1ea$0$0$225
Slab Saw-Cut and Trench (per lf)6lf2 to 6 h$288$0$288
Slab Trench Patch Labor6lf1 to 2 h$102$0$102
Slab Trench Patch Materials (per lf)Labor on: Slab Trench Patch Labor6lf$0$63$63
Vent Extension Labor1ea2 to 6 h$425$0$425
Plumbing subtotal17 to 25 h$4,006
Plumbing subtotal17 to 25 h$4,006
DIRECT JOB COST20 to 29 h$4,231
DIRECT JOB COST20 to 29 h$4,231

E. Up-flush toilet: $3,132

A macerating toilet with a sink into it, 12 ft of discharge and a vent; no concrete cutting. Labor is $1,615 of the $3,132 job cost, or 51.6%. It is about 12 to 18 hours of work, including setup, daily cleanup and material runs.

Labor cost by trade

Labor only. Materials, allowances and dump fees are in the line items below. Hours are person-hours at typical production from Clamp’s labor hours catalog, as a range: a planning figure, not a schedule and not a charge to the customer.

TradeHoursLabor costLean×1.30Standard×1.50Full-Service×2.00
Plumbing10 to 16 h$1,615$2,100$2,423$3,230
Setup, cleanup and material runs1 to 3 hin the prices
All labor12 to 18 h$1,615$2,100$2,423$3,230

Every line item

Labor $1,615 + materials and allowances $1,517 + dump fees and other $0 = $3,132 direct job cost. Hours are person-hours at typical production, on labor rows only, and the direct-cost row adds about 15% for setup, daily cleanup and material runs; an allowance or material row names the labor line that installs it, and a subcontract row has none, because the sub’s price includes their own time. Some labor quantities include a difficulty factor, so they can exceed the measured area; each row’s derivation is in the downloadable data.

ItemQtyUnitHoursLaborMaterialLine cost
Plumbing
Drain Water Test and Rough-In Inspection (per job)1ea1 to 2 h$325$0$325
DWV Install Labor7lf2 to 6 h$315$0$315
Up-Flush Macerating Toilet Package1ea$0$1,400$1,400
DWV MaterialsLabor on: DWV Install Labor18.7lf$0$117$117
Sewage Ejector Install1ea2 to 6 h$550$0$550
Vent Extension Labor1ea2 to 6 h$425$0$425
Plumbing subtotal10 to 16 h$3,132
Plumbing subtotal10 to 16 h$3,132
DIRECT JOB COST12 to 18 h$3,132
DIRECT JOB COST12 to 18 h$3,132

F. Raised platform over the drains: $1,222

A 6 by 8 ft platform framed high enough for gravity drains, with a two-riser step; plumbing by others. Labor is $855 of the $1,222 job cost, or 70.0%. It is about 10 to 18 hours of work, including setup, daily cleanup and material runs.

Labor cost by trade

Labor only. Materials, allowances and dump fees are in the line items below. Hours are person-hours at typical production from Clamp’s labor hours catalog, as a range: a planning figure, not a schedule and not a charge to the customer.

TradeHoursLabor costLean×1.30Standard×1.50Full-Service×2.00
Carpentry8 to 16 h$855$1,112$1,283$1,710
Setup, cleanup and material runs1 to 3 hin the prices
All labor10 to 18 h$855$1,112$1,283$1,710

Every line item

Labor $855 + materials and allowances $367 + dump fees and other $0 = $1,222 direct job cost. Hours are person-hours at typical production, on labor rows only, and the direct-cost row adds about 15% for setup, daily cleanup and material runs; an allowance or material row names the labor line that installs it, and a subcontract row has none, because the sub’s price includes their own time. Some labor quantities include a difficulty factor, so they can exceed the measured area; each row’s derivation is in the downloadable data.

ItemQtyUnitHoursLaborMaterialLine cost
Carpentry
Platform Step at the Door (per step)1ea1 to 4 h$285$0$285
Platform Step Materials (per step)1ea$0$48$48
Sleeper Floor Over Slab, Framing Labor (per sf)48sf6 to 13 h$570$0$570
Sleeper Floor Over Slab, Materials (per sf)Labor on: Sleeper Floor Over Slab, Framing Labor (per sf)48sf$0$319$319
Carpentry subtotal8 to 16 h$1,222
Carpentry subtotal8 to 16 h$1,222
DIRECT JOB COST10 to 18 h$1,222
DIRECT JOB COST10 to 18 h$1,222

G. Laundry sink, 10 ft trench: $3,659

10 ft of trench, a 2 in drain tied into the old drain, a vent, water lines and the sink set. Labor is $2,850 of the $3,659 job cost, or 77.9%. It is about 24 to 32 hours of work, including setup, daily cleanup and material runs.

Labor cost by trade

Labor only. Materials, allowances and dump fees are in the line items below. Hours are person-hours at typical production from Clamp’s labor hours catalog, as a range: a planning figure, not a schedule and not a charge to the customer.

TradeHoursLabor costLean×1.30Standard×1.50Full-Service×2.00
Plumbing20 to 28 h$2,850$3,705$4,275$5,700
Setup, cleanup and material runs1 to 6 hin the prices
All labor24 to 32 h$2,850$3,705$4,275$5,700

Every line item

Labor $2,850 + materials and allowances $359 + dump fees and other $450 = $3,659 direct job cost. Hours are person-hours at typical production, on labor rows only, and the direct-cost row adds about 15% for setup, daily cleanup and material runs; an allowance or material row names the labor line that installs it, and a subcontract row has none, because the sub’s price includes their own time. Some labor quantities include a difficulty factor, so they can exceed the measured area; each row’s derivation is in the downloadable data.

ItemQtyUnitHoursLaborMaterialLine cost
Demo & Prep
Debris Haul-Off (per Load)1ea$0$0$225
Demo & Prep subtotal$225
Demo & Prep subtotal$225
Plumbing
Below-Slab Drain Pipe Install (per lf)10lf1 to 5 h$340$0$340
Drain Water Test and Rough-In Inspection (per job)1ea1 to 2 h$325$0$325
Fixture Set Labor1ea1 to 4 h$325$0$325
Utility Sink Trap and SuppliesLabor on: Fixture Set Labor1ea$0$45$45
Tie-In Wye and Transition Couplings (per tie-in)1ea$0$98$98
DWV MaterialsLabor on: Plumbing Rough-In Per Fixture11lf$0$69$69
Plumbing Rough-In Per Fixture1ea1 to 3 h$225$0$225
Supply Pipe MaterialsLabor on: Plumbing Rough-In Per Fixture12lf$0$42$42
Slab Cutting Equipment and Dust Control (per job)1ea$0$0$225
Slab Saw-Cut and Trench (per lf)10lf4 to 10 h$480$0$480
Slab Trench Patch Labor10lf1 to 3 h$170$0$170
Slab Trench Patch Materials (per lf)Labor on: Slab Trench Patch Labor10lf$0$105$105
Tie In to the Existing Cast Iron or Clay Drain (per tie-in)1ea1 to 4 h$560$0$560
Vent Extension Labor1ea2 to 6 h$425$0$425
Plumbing subtotal20 to 28 h$3,434
Plumbing subtotal20 to 28 h$3,434
DIRECT JOB COST24 to 32 h$3,659
DIRECT JOB COST24 to 32 h$3,659

H. Camera and locate first: $325

Camera the main from the cleanout, locate it and mark its direction and depth on the floor. Labor is $325 of the $325 job cost, or 100.0%. It is about 1 to 2 hours of work, including setup, daily cleanup and material runs.

Labor cost by trade

Labor only. Materials, allowances and dump fees are in the line items below. Hours are person-hours at typical production from Clamp’s labor hours catalog, as a range: a planning figure, not a schedule and not a charge to the customer.

TradeHoursLabor costLean×1.30Standard×1.50Full-Service×2.00
Plumbing1 to 2 h$325$423$488$650
Setup, cleanup and material runsunder 1 hin the prices
All labor1 to 2 h$325$423$488$650

Every line item

Labor $325 + materials and allowances $0 + dump fees and other $0 = $325 direct job cost. Hours are person-hours at typical production, on labor rows only, and the direct-cost row adds about 15% for setup, daily cleanup and material runs; an allowance or material row names the labor line that installs it, and a subcontract row has none, because the sub’s price includes their own time. Some labor quantities include a difficulty factor, so they can exceed the measured area; each row’s derivation is in the downloadable data.

ItemQtyUnitHoursLaborMaterialLine cost
Plumbing
Camera Inspection Labor1ea1 to 2 h$325$0$325
Plumbing subtotal1 to 2 h$325
Plumbing subtotal1 to 2 h$325
DIRECT JOB COST1 to 2 h$325
DIRECT JOB COST1 to 2 h$325

Methodology & reproducibility

8 snapshots, one per build. Each build is frozen from its own estimate run with the same old work, system type and takeoff pinned, so the builds differ only in what is being built.

Direct cost equals the sum of each row’s rounded quantity × (labor + material + other). Amounts are shown in whole dollars; every column adds to its total.

Scope selection, prose accuracy, arithmetic and provenance mapping reviewed; not independent market-rate verification.

Questions

How much does it cost to cut a basement floor for plumbing?

A 12 ft trench through a 4 in slab, cut wet, broken out, dug 18 in deep, hauled away and patched after the plumber is done, is $1,356 in job cost, $1,763 to $2,712 from a contractor. That is the concrete work alone. The saw cut is about 27 ft for 12 ft of trench, because both sides and the ends are cut.

What do the drains for a basement bathroom cost?

A toilet, shower and sink in 20 ft of trench, tied into the existing 4 in drain, water-tested, inspected and patched: $4,186 in job cost, $5,441 to $8,371 from a contractor. HomeGuide puts an ordinary one-bathroom rough-in at $1,500 to $3,000 before any slab cutting; Oakwood Remodeling puts cutting the slab and rerouting drains at $3,000 to $8,000.

What slope does a basement drain need?

Under the International Plumbing Code, 1/4 in per ft for 2 in pipe and 1/8 in per ft for 3 in and larger. A 12 ft run of 2 in drain drops 3 in before the fittings and trap. Uniform Plumbing Code (UPC) areas generally want 1/4 in per ft and allow 1/8 in only on 4 in and larger with approval. Your local code controls.

What if the sewer is too shallow for a basement toilet?

There are three fixes. A sewage ejector basin and pump in the slab is $4,231 in job cost before the drains to it; HomeGuide puts a new system at $2,000 to $5,500. An up-flush macerating toilet is $3,132 with a sink into it, more than HomeGuide's $1,000 to $2,000 because this one includes the vent and 12 ft of discharge. A raised platform over gravity drains is $1,222 for the framing alone.

Does an up-flush toilet need a vent?

Yes. Saniflo's instructions call for a vent connection on the pump and no air admittance valve on that vent, and a shower draining into it sits on a raised base so its trap can drain. No concrete cutting is the main saving.

How high can a bathroom platform be?

Only as high as the headroom allows. The residential code asks for 6 ft 8 in of ceiling height in a bathroom, so a 7 ft 6 in basement leaves about 10 in for the platform and floor. The step up needs two risers, since one riser cannot be over 7 3/4 in. Check the toilet, trap and fall to the main fit under it before you build.

What does tying into the old cast iron stack cost?

Opening the floor 3 by 3 ft at the stack, cutting in a wye with couplings matched to the cast iron and the clay, adding a cleanout, testing and patching: $2,344 in job cost. Use a shielded coupling on the cast iron and a transition rated for clay to plastic under the slab. If the cast iron crumbles or the clay is broken, more pipe has to be replaced.

What about just a laundry sink?

A laundry sink 10 ft from the drain, with the trench, a 2 in drain, a vent, the water lines and the sink set: $3,659 in job cost, $4,756 to $7,318 from a contractor. Most of the cost is the trench and the tie-in, not the sink.

Should I have the drain camera-inspected first?

Yes. A camera run from the cleanout, with the line located and marked on the floor, is $325 in job cost. HomeGuide puts a camera inspection at $125 to $500. Without it you can cut a trench to the wrong place or find the drain too shallow after the floor is open. A locator's depth is an estimate, so confirm the depth before you cut.

Is wet cutting a basement slab dust-free?

No. Water cuts most of the dust, but OSHA's silica rule still calls for respiratory protection for indoor wet sawing. Use an electric saw indoors, never a gas saw, because of carbon monoxide. Every slab job here includes a $225 equipment and dust-control line.

Is the markup on top of these numbers?

Yes. Direct job cost is what the work costs a contractor to do. The markup table shows what it sells for at illustrative markups of 30% to 100%, from a low-overhead owner-operator to a full-service firm. Permits are shown separately.

Related

Sources & provenance

  1. Ejector Pump Cost HomeGuide (research)
  2. Toilet Installation Cost HomeGuide (research)
  3. Sewer Camera Inspection Cost HomeGuide (research)
  4. Cost to Install New Plumbing Pipes HomeGuide (research)
  5. 1950s Ranch Home Bathroom Remodel, Sacramento Oakwood Remodeling (research)
  6. 2021 International Plumbing Code, Chapter 7: Sanitary Drainage International Code Council (official source)
  7. 29 CFR 1926.1153, Respirable crystalline silica OSHA (official source)
  8. Saniflo professional catalog Saniflo (research)
  9. 12 ft trench, concrete only reviewed snapshot Clamp Research
  10. Bathroom drains, 20 ft reviewed snapshot Clamp Research
  11. Tie-in at the cast iron stack reviewed snapshot Clamp Research
  12. Sewage ejector pit reviewed snapshot Clamp Research
  13. Up-flush toilet reviewed snapshot Clamp Research
  14. Raised platform over the drains reviewed snapshot Clamp Research
  15. Laundry sink, 10 ft trench reviewed snapshot Clamp Research
  16. Camera and locate first reviewed snapshot Clamp Research
Changes: Oct 15, 2026: Initial publication: eight basement slab and drain jobs frozen from estimate runs on the October 2026 estimator, with published installed prices.; Oct 15, 2026: The direct answer quotes the concrete work alone and a bathroom's drains, not the camera inspection and the ejector.; Nov 10, 2026: Search Console pass: the title and the summary carry the price range the answer gives. No job cost changed.; Nov 10, 2026: Repriced at the November 2026 catalog from the same saved estimate runs. The tie-in to the existing drain is $560 (was $350), the water test and rough-in inspection $325 (was $175), the slab patch $17 a foot (was $14) and the cutting equipment line $225 (was $195). The camera inspection is unchanged.